1.1 Project Identification
Title block / document control69 stations. Follows the project city until you pick one.
1.2 Design Criteria & Statutory Basis
NBCS 2026 Pt.E · CPHEEO · NGT 2019Shown beside the total demand in section 03, the DBR and the Excel export — for information only. Tanks, pumps, sewage and the STP stay on the full demand. Pool, cooling-tower and boiler make-up, process water and fire top-up stay at 100 %.
Codes & Standards in Force
The documents this tool draws on. Selecting them moved no calculation, so the picker is hidden rather than kept as a control that does nothing — the declaration still travels in the project and the report still schedules it.
Edit the declared document stack
1.3 Raw / Source Water Analysis
IS 3025 · IS 10500:2012 as amended June 2015The label you navigate by
What actually decides the chemistry
1.4 Vastu Placement Guidance
Traditional · not a code2.1 Site
The land and the project — the same fields as 1.1, edited in either place2.2 Buildings, Floors & Areas
Building → Floor → Area → Usage · occupancy inherited downwards
Areas shown in
2.3 Population & PHE Inputs
NBCS 2026 Pt.E Sec.1 Cl.4.1 · Table 1 · Sec.2 Tables 1–17 — what 03 onwards is built on2.4 Blocks & Direct Line Items
A use type from the rates library × a quantity in that rate's own unit — persons, keys, kg, m², TR-hr, tonnes2.5 Master Data & Project Criteria — occupancies, sub-occupancies, usages, area types
3.0 Design Basis — Method, Settings & Rates
The governing code, the rates library in force, the settings every design figure is sized on — design factors, storage rules of thumb and assumptionsShown, each building and site block may keep its own usage hours and peak factor.
Design Factors & Notes — the firm's rules of thumb beside this project's figures
Rounding (display only), report caveats & code references
Every figure is carried at full precision; these places are what the screen, the report and the workbook print.
3.1 Domestic Water Demand
NBCS 2026 Pt.E Sec.1 Cl.4.1.1 · Table 1 — occupancy from the schedule in 02Hot Water Requirement & Generation
Cl.4.14.3 sizes storage on the maximum short time demand — the morning peak — not the day's average: 50–75 L at 60 °C for a dwelling with a bath tub, 25 L for a shower or tap, and the vessel not less than 20 % in excess. Enter the dwellings served and the Standard's basis governs; the percentage-of-daily figure below is kept only as a cross-check and is not a Cl.4.14 basis.
Basis: Q = m × Cp × ΔT / t, with Cp = 4.186 kJ/kg·K and water at 1000 kg/m³. The result is heat at the point of transfer — add generation efficiency, standing loss and a simultaneity allowance before selecting a heat pump, solar thermal array or calorifier. Storage below 60 °C is a legionella risk; use thermostatic mixing at the outlets rather than lowering the store.
Nos. is the count of units the rate is multiplied by, in whatever the Basis column names — beds for a hotel, persons for an office. Enter it directly, or leave it to be computed as Rooms × Occupancy per Room. Hot and Cold are the two figures you set, and Domestic is their sum. The one you are not typing holds still, so raising the hot demand does not silently move the cold. Click ▸ on any row to open its end uses — bathing, kitchen, laundry, and so on for that building type; overwriting a rate rescales that split so the breakdown still adds up to the row. Table 1 states a minimum, so a higher rate is a legitimate design decision — the cell shows the code figure beneath it and the report lists every departure as the project’s own.
3.2 Non-Domestic & Ancillary Demands
CTI/ASHRAE · GRIHA landscape · NBC Pt.4 (fire)Landscape & Horticulture Irrigation
HVAC Cooling Tower Make-up
Basis: E = 0.00085 × 1.8 × ΔT(°C) × Circulation (m³/h) | B = E/(COC−1) − D | M = E + D + B = E·COC/(COC−1). Blowdown is routed to the STP inlet where quality permits; otherwise to drain.
Swimming Pool / Water Bodies
Cl.4.19 sizes the pool properly: user load from surface area, turnover rate by pool type, filter area from the filtration rate, and backwash at not less than 30 m³/m²/h. Make-up is evaporation plus that backwash. Evaporation itself carries no NBCS figure by either route — a rate over the water surface is the physical basis, a share of the pool volume is what many briefs ask for, and whichever is chosen is stated in the report as the project's own allowance.
Shower area. Showers beside the pool — a supply the pool's own fill, make-up and backwash never carry. Number of showers × litres per minute is a flow: what the main and the hot water plant carry at once. It becomes a daily volume, and joins the demand, only once the minutes of use are stated. The litres per minute opens at the Standard's figure for the fittings set in 1.2.
Process / Industrial & Miscellaneous Demands
| Description | Water Quality | Demand KLD | Return to Effluent % | Effluent KLD |
|---|
Fire Fighting Static Storage (not a recurring demand)
Per NBCS 2026 Part F — Fire and Life Safety, to which NBCS 2026 Pt.E/Sec.1 Cl.4.1.4 refers the firefighting requirement, static storage is dedicated and excluded from the daily water balance; only make-up for evaporation/testing is accounted. Fire tank first-fill must however be included in the source capacity assessment.
3.3 Consolidated Water Demand Summary
Peak day demand3.4 Block-wise Water Demand & Design Summary
Every line in every block · Total = Q × total rate · Domestic = Total − Flushing · Wastewater = Total × return factor4.1 Wastewater Generation — Stream-wise
NBCS 2026 Pt.E Sec.2 · CPHEEO Sewerage Manual 2013 Pt.A Cl.3.3
Return factors are editable. Default basis: domestic 85 %, flushing 100 %, kitchen 90 %, landscape 0 % (fully consumed), cooling tower — blowdown only, pool — backwash only.
4.2 Design Flow Check & STP Capacity Selection
Dual check — stream-wise vs. CPHEEO 80 % rule4.3 Sanitary Fixture Provision — Male, Female, Accessible
NBCS 2026 Pt.E Sec.2 Cl.4.2.5.1 · Tables 1 to 174.4 Drainage Design
NBCS 2026 Pt.E Sec.2 Cl.4.5.3.5.1 · Tables 18, 20, 22–25Fixture units per Table 20; stack from Table 18 by building height; branch from Table 22; building drain from Table 23 by slope; gradients from Table 24. Enter the fixture counts you have worked up from the provision schedules in the report — the tool does not derive them, because Tables 1–17 are reproduced rather than computed from.
| Fixture — Table 20 | Private | Public | Unit Value | DFU | Min Trap mm |
|---|
4.5 Grease Traps
NBCS 2026 Pt.E Sec.2 Cl.4.5.6 — required, and not sized by the clause4.6 Solid Waste Management
NBCS 2026 Pt.E Sec.3 Cl.5.1 · 4.3 · 6.2.1Cl.5.1 gives each generation rate as a range; the midpoint is used unless you enter a project rate. The total divides 60 % organic / 40 % inorganic. Waste follows people, so beds, seats and passengers contribute only through the population in the occupancy schedule.
5.1 Plants & Occupancy Grouping
Any number of plants; each occupancy drains to the one you assign it toWhich occupancy drains to which plant
5.2 Influent Characteristics & Treated Water Standard
CPHEEO 2013 Pt.A Table 3.5 · NGT dt.30.04.20195.3 Technology Selection Matrix
Weighted evaluation — capacity, footprint, reuse, O&M0 = unconstrained
0 = show kWh only
For the cheapest route on the sheet
ZLD evaporation only
5.4 Unit Process Design & Sizing
CPHEEO 2013 Pt.A Ch.5 · Metcalf & Eddy5.5 Aeration, Sludge & Power
Oxygen demand · sludge yield · connected load5.6 Equipment Schedule — STP
6.1 Treatment Train Requirement — driven by source analysis
IS 10500:2012 acceptable / permissible limits6.2 Water Treatment Plant (WTP)
CPHEEO Water Supply Manual · IS 84196.3 Water Softening Plant
Strong Acid Cation (Na⁺ cycle) · IS 8419 Pt.2Range 40–70 (≈18–30 kgr/cft)
6.4 Reverse Osmosis Plant
Brackish water RO · IS 10500 permeate target6.5 Demineralisation (DM) Plant
SAC + Degasser + SBA (+ Mixed Bed)7.1 Effluent Source & Characterisation
EPA 1986 Sch.VI (CPCB General Standards)7.2 Process Route — Selection and Comparison
Derived from the effluent's own BOD:COD, COD, oil load and TDS7.3 Recommended Treatment Scheme
7.4 Zero Liquid Discharge Block
RO → MEE → ATFD8.1 Water Mass Balance Schematic
All flows in KLD (m³/day), peak-day basis
Fresh / Potable water
Softened / DM / RO water
Raw wastewater / effluent
Treated & recycled water
Losses / disposal
8.2 Mass Balance Reconciliation
Inflow = Outflow ± storage9.1 Water Storage Schedule
NBCS 2026 Pt.E Sec.1 Cl.4.4.10 · Part F (fire)9.2 Pump Schedule
Duty + standby; head computed per CPHEEO Pt.A where a pipe run is enteredPumping hours — each sets the hours a transfer pump's day is pumped in, so its duty flow is the daily volume ÷ these hours
10.1 Rainwater Harvesting & Recharge
CGWA 2020 · MoEFCC EIA Notification 2006 · IS 15797Shaft 10–20; trench 4–8. Confirm by percolation test.
10.2 Storm Water Calculation
NBCS Cl.4.5.11.2 · IRC:42 Cl.6.3, 6.4.2 · IRC:SP:1310.3 Storm Water Storage
A volume to hold on site — a green rating requirement, not a code one11.1 Green Rating — Water Performance Scorecard
LEED v4.1 BD+C · IGBC GNB v3.0 · GRIHA v2019 — water credits onlyLEED measures against its own fixture schedule, not the NBCS rate